Time Core · Contingency Planning · Module

Decision points

When the choice between continuing and changing course has to be taken — derived from the lead time of the alternatives rather than from the deadline.

The idea

How it works

The decision point is the deadline minus the fallback’s lead time. After it, continuing is not a choice but the only remaining option.

Setting it in advance is what converts a delay from something that happens into something that is decided about, and it is the single most useful thing in this object.

Working with it

In practice

  1. 01

    Work backwards from the fallback

    Deadline minus lead time. That date is when the decision has to be taken.

  2. 02

    Define what would trigger the switch

    A measurable state at that date, agreed beforehand, so the call is not made on optimism.

  3. 03

    Put it in the calendar

    A decision point nobody has diarised is a decision point that passes.

  4. 04

    Make the call

    On the date, on the agreed criterion. Deferring it is a decision to continue.

One level in

The components of decision points

A component is something that exists afterwards which did not exist before — a deliverable or a mechanism, not an intention.

  1. The date

    When the decision has to be taken.

    Learn
  2. The criterion

    What state at that date would trigger the fallback.

    Learn
  3. The decision

    What was decided, when, and on what basis.

    Learn

Deferring a decision point is a decision to continue. It just does not feel like one.