Undefined scope is the most common cause of failure
Not scope that changed, which is normal, but scope that was never agreed and turned out to mean different things to different people.
Time Core · Object
Getting defined work done by a date: agreeing what it is, sequencing what depends on what, running it, and ending it properly.
The term
A project is work with an end. That distinguishes it from operations and is what makes it manageable — and it is also why the definition of done has to exist before anything starts.
Almost all project failure traces to one of three things: the work was not what everyone thought it was, something it depended on was not ready, or the estimate was made by someone who would not have to meet it.
The part with the largest return and the least attention is closure. A project that ends without anyone establishing what happened teaches nothing, and the next estimate is made with the same information as the last one.
Why it earns a place
Not scope that changed, which is normal, but scope that was never agreed and turned out to mean different things to different people.
A project of six weeks of work can take six months if it waits on three things it does not control, and the plan usually shows only the work.
An organisation that does not compare its estimates with its outcomes is making the same errors indefinitely and calling it optimism.
One level in
Four working areas following a project’s life: agreeing what it is, working out the order, running it, and ending it in a way that improves the next one.
What is being done, what is not, and what would count as finished. The agreement that everything downstream depends on and that is routinely assumed rather than made.
LearnHow progress is established, how change is handled, and how a problem becomes visible before the deadline rather than at it.
LearnAcross the framework
Beyond the framework
The Omnigoal says where this belongs and what it touches. It does not tell you how to think about it — other people have done that, and done it well. These are theirs.
Also known as CPM, Critical path
The longest chain of dependent tasks sets the finish date, and only that chain does.
Everything else has slack. The practical consequences are unintuitive and reliably ignored: adding people to a task off the critical path changes nothing, a delay on the path is a delay to the project, and the path itself moves as work progresses, so it has to be recalculated rather than drawn once.
James E. Kelley & Morgan R. Walker, “Critical-Path Planning and Scheduling”, Eastern Joint Computer Conference, 1959.
Work proceeds in stages separated by decision points where a project can be stopped.
Each gate asks the same three questions — is it still worth doing, are we doing it well, and what would justify continuing — with criteria agreed before the answer is known. The gate that matters is the one where a project is killed, and its absence is why organisations carry projects nobody believes in for years.
Robert G. Cooper, Winning at New Products, Addison-Wesley, 1986.
Fixed short cycles producing something usable, with the plan reconsidered at the end of each one.
A deliberately small set of roles, events and artefacts built on the assumption that requirements will be wrong and are best corrected by evidence rather than by analysis. Its most valuable and least practised element is the retrospective, which is the only part that changes how the team works rather than what it produces.
Ken Schwaber, “SCRUM Development Process”, OOPSLA ’95; Schwaber & Sutherland, The Scrum Guide, from 2010.
Also known as Responsible, accountable, consulted, informed
For each task, name who does it, who answers for it, who must be asked and who must be told.
The distinction that earns its keep is between responsible and accountable: several people can do the work, but exactly one answers for whether it happened. Most of the value appears while filling it in, when it turns out two people believed they were accountable for the same thing, or nobody was.
Long-standing practice in project management; documented in the PMBOK Guide, Project Management Institute.
Every task drawn as a bar against a calendar, so that duration, overlap and sequence can be seen at once.
More than a century old and still the default way work is shown over time. What it does well is expose two things that are invisible in a task list: how much is happening at the same moment, and which things cannot start until something else finishes. Adding the dependencies is what turns it from a picture into a plan.
Developed by Henry L. Gantt around 1910–1915; a similar chart was published by Karol Adamiecki in 1896.
These are other people’s models, named here so you can go to the source and use them properly. The Omnigoal is not affiliated with their authors and is not endorsed by them; nothing of theirs is reproduced here — no canvas, no diagram, no wording. Each is described in our own words, with the originator credited, because the framework is a place to put thinking, not a replacement for the people who did it. Model names and trademarks belong to their respective owners and are used here only to refer to the work itself.
Every model in the framework, and where each one belongsAn organisation that never compares its estimates with its outcomes is making the same errors indefinitely.
Determines the optimal time for launching new products or entering new markets. This is key for capitalising on market opportunities and achieving a competitive edge.
LearnIdentifies and capitalises on unique, high-impact opportunities that arise unexpectedly. This ensures the business can quickly leverage these opportunities for maximum benefit.
LearnPrepares for unexpected events and disruptions by developing plans to mitigate risks and ensure business continuity. This helps the organisation remain resilient and responsive.
LearnProvides a visual and strategic overview of the year, outlining key activities, milestones, and events. This ensures that the business remains focused and aligned throughout the year.
Learn