The change log

What was added or changed, and what it cost in time — because absorbing changes without adjusting the date is how projects slip invisibly.

The deliverable

What it is

A project can be delivered exactly as planned and be three months late, because it absorbed eleven changes each too small to justify moving the date.

The log makes the accumulation visible, and it is the answer to the question of why the project is late.

One level in

What it is made of

Each element is a constituent part of the component. Follow one to see the attributes it carries.

  1. The entries

    Each change during delivery.

    3 attributes: Change · Date · How agreed

    Learn
  2. The time cost

    What each added.

    3 attributes: Time added · Running total · Absorbed

    Learn
  3. The explanation

    What the log says about the project.

    3 attributes: Total slip · Explained by change · Unexplained

    Learn

A project late by exactly the sum of its logged changes was delivered as planned. That is a scope finding.