Project management · Running it · Component

The progress measure

What is actually finished, established rather than reported — because percentage complete is an opinion.

The deliverable

What it is

Self-reported percentage complete rises steadily to ninety and then stops, which is the recognisable signature of the measure being an estimate of effort spent rather than of work finished.

Counting things that are actually done — verified, accepted, working — is harder to report and considerably more honest.

One level in

What it is made of

Each element is a constituent part of the component. Follow one to see the attributes it carries.

  1. The completed

    What is finished and verified.

    3 attributes: Items complete · Total items · Verified

    Learn
  2. The comparison

    Progress against elapsed time.

    3 attributes: Work complete · Time elapsed · Gap

    Learn
  3. The remaining

    What is left and how long it will take.

    3 attributes: Remaining estimate · Original remaining · Re-estimated

    Learn

Forty per cent of the work with sixty per cent of the time elapsed is the finding, and it needs only counting.